Planning Permission and Building Regulations: A Due Diligence Guide
Before buying, extending, converting or redeveloping property, check the planning status of the land and the separate building control requirements. This guide explains the questions to ask and the records to obtain. It is not a report on any particular site or a summary of all recent rule changes.
1. Establish the lawful existing use
Identify the planning unit, the established lawful use, previous permissions and conditions, and whether a lawful development certificate exists or is needed. A commercial description, estate agent particulars or historic use alone may not prove that a proposed use is lawful.
2. Check whether planning permission is required
Consider the development proposed, any applicable permitted development rights, restrictions such as Article 4 directions, conservation areas and listed building status. Changes of use, extensions, additional dwellings and external works may require different permissions. Where permitted development is relevant, check its exact limitations and whether prior approval is required.
3. Review the planning history and obligations
Obtain decision notices, approved drawings, discharge of conditions, planning obligations and enforcement records from the local planning authority. Check Community Infrastructure Levy exposure where relevant and any conditions that must be met before commencement, occupation or other milestones.
4. Distinguish planning from building regulations
Planning consent does not establish compliance with building regulations. Discuss structural safety, fire safety, energy efficiency, ventilation, drainage and accessibility with a competent designer and building control professional. Check the appropriate building control route, approvals, inspection records and completion documentation.
5. Identify higher-risk and specialist issues
Depending on the project, investigate flood risk, highways access, trees, biodiversity requirements, contamination, heritage restrictions, party wall matters, rights of light, easements, restrictive covenants, lease restrictions and utility capacity. Higher-risk buildings can be subject to additional building safety procedures.
6. Obtain a complete project document pack
- Title register, title plan, relevant leases and easements
- Planning history, decision notices, approved plans and condition-discharge evidence
- Lawful development certificates and prior approval decisions, if relevant
- Building control applications, inspection records and completion certificates
- Professional drawings, structural assessments, warranties and insurance details
- Planning obligations, CIL correspondence and enforcement information
7. Practical scenarios and red flags
House extension: Check the permitted development limits, previous extensions, boundary constraints, drainage and building control before instructing builders. A permitted development project may still need other approvals.
Shop-to-residential conversion: Verify the existing lawful use, whether the proposed change is permitted, any prior approval conditions, minimum standards, lease restrictions and financing implications. Do not assume a change of use is automatic.
Subdivision into flats: Examine planning consent for the number of units, fire and sound requirements, access, utilities, title arrangements, mortgage consent and service charge structure.
Buying a development site: Investigate planning conditions, CIL, section 106 obligations, biodiversity net gain where applicable, highway works, contamination, utilities and the risk of judicial review or enforcement.
8. Questions to ask your solicitor and planning consultant
- What is the lawful existing use, and what documentary evidence supports it?
- Which consents and prior approvals are needed for the exact proposed works?
- Are there undischarged conditions, enforcement notices or planning obligations?
- Are there separate building control, listed building or landlord approvals?
- What must be completed before commencement or occupation?
- Which planning and title risks should be addressed in the purchase contract?
9. Planning and building control are not the same as ownership rights
Even where a development has planning consent, private-law restrictions may prevent it. Check covenants, easements, leasehold consent, party wall requirements and neighbouring rights separately. Conversely, a title right to build does not establish that the planning authority will approve the works.
10. Sequence decisions before spending
Ask the local planning authority about relevant constraints; instruct planning and technical specialists where appropriate; assess the cost and time of conditions and building control compliance; and make any purchase or building contract conditional on suitable due diligence where commercially possible. Do not assume retrospective consent will be available.
Official starting points
- Planning Portal — Do you need permission?
- GOV.UK — Planning permission
- GOV.UK — Building regulations approval
- GOV.UK — Planning practice guidance
Kim Partners Solicitors